2018 May Latest Microsoft 70-713 Exam Dumps with PDF and VCE Just Updated Today! Following are some new 70-713 Real Exam Questions:

1.|2018 Latest 70-713 Exam Dumps (PDF & VCE) 52Q Download:
https://www.braindump2go.com/70-713.html

2.|2018 Latest 70-713 Exam Questions & Answers Download:
https://drive.google.com/drive/folders/0B75b5xYLjSSNSUxBWUxwdmJyTUU?usp=sharing

QUESTION 23
You represent a SAM partner.
A client must consolidate their IT departments into a single business unit.
The client was previously assessed in the Microsoft SAM Optimization Model {SOM) key competencies and assigned the maturity level of Standardized.
You need to ensure that the client progresses to the next SOM level in the Deployment Process key competency.
What should the client do?

A. Purchase software only from approved vendors.
B. Publish software deployment reports to stakeholders.
C. Use information provided by a software publisher.
D. Use software metadata generated by the client.
E. Deploy only approved software.
F. Formulate a retirement process.
G. Create an inventory of deployed assets.
H. Maintain updated records of deployed assets.

Answer: B
Explanation:
http://download.microsoft.com/download/3/5/4/354b34f9-320c-42f1-b56d-ce4282ddb796/sam_optimization_brochure_direct-to-customer_us.pdf Page: 7 (Deployment Process).

QUESTION 24
This question requires that you evaluate the underlined text to determine if it is correct.
You are performing a SAM baseline review for a customer.
You need to review the data collected for cloud and on-premises hardware and software.
The Established Deployment Position (EDP) report provides detailed information on the licenses the customer has purchased and how they are allocated in the environment.
Review the underlined text. If it makes the statement correct, select "No Change' is needed." If the statement is incorrect, select the answer choice that makes the statement correct.

A. No change is needed
B. Effective License Position <ELP) report
C. Microsoft Assessment and Planning Toolkit (MAP) software usage reports
D. Licensing Optimization Recommendations report

Answer: A

QUESTION 25
This question requires that you evaluate the underlined text to determine if it is correct.
An organization implements a SAM program based on the ISO 19770-1 specification.
The organization conducts a review of inventory data once each calendar year and reconciles data from multiple sources.
The organization has achieved Tier 2 of the ISO specification.
Review the underlined text. If it makes the statement correct, select "No change is needed." If the statement is incorrect, select the answer choice that makes the statement correct.

A. No change is needed.
B. Tier 1
C. Tier 3
D. Tier 4

Answer: B

QUESTION 26
Your customer's Acquisition Process key competency has Basic maturity level.
You need to recommend a process to improve the Acquisition Process maturity level.
Which process should you recommend?

A. Collect entitlement records throughout the organization.
B. Require an annual sign-off on all SAM reports.
C. Reuse licenses as computers are retired.
D. Require that software purchases be made from approved vendors.

Answer: D

QUESTION 27
Your customer has a SAM program. The customer installs SAM tools that monitor approved software installations.
You need to monitor whether the customer adheres to approved software installation policies.
What should you do?

A. Perform quarterly license metering verifications.
B. Perform quarterly inventory verifications.
C. Perform quarterly hardware inventory verifications.
D. Perform quarterly human resources audits for new employees.

Answer: A

QUESTION 28
You maintain a SAM program for a customer. The customer experiences the following recent developments:
- A new SAM tool is purchased.
- The SAM program design is complete.
- The assigned SAM manager leaves the company.
- The SAM program budget is approved and allocated.
You need to maintain the SAM program.
What should you do first?

A. Secure executive sponsorship.
B. Secure the support of the IT department.
C. Recommend starting a new SAM program.
D. Generate a Microsoft Product License Advisor (MPLA) report.

Answer: A

QUESTION 29
You are designing a SAM improvement program. The focus of the program is to address deficiencies in the software purchasing process.
Stakeholders report that managers are purchasing Software-as-a-Service (SaaS) app subscriptions on their corporate credit cards and submitting the costs on monthly expense reports.
You have the following requirements:
- Improve governance of the purchasing process.
- Reduce recurrence of the problems reported.
- Minimize impact to other business activities.
You need to recommend steps to improve the organization's purchasing process.
Which three actions should you recommend? Each correct answer presents part of the solution. Note: Each correct selection is worth one point.

A. Only approve software purchases from authorized suppliers.
B. Collect all historical procurement data.
C. Conduct user awareness training.
D. Centralize purchasing within the organization.
E. Revoke purchasing privileges for managers expensing licensing purchases.

Answer: ABE

QUESTION 30
You need to monitor infrastructure and manage software deployments for an organization.
You must uninstall unlicensed software from all devices.
Which tool should you use?

A. Microsoft Intune
B. Microsoft Assessment and Planning Toolkit (MAP)
C. System Center Configuration Manager (ConfigMgr)
D. Mircrosoft Desktop Optimization (MDOP)

Answer: C

QUESTION 31
This question requires that you evaluate the underlined text to determine if it is correct.
Your customer needs to reclaim unused software licenses.
You recommend Microsoft Intune as a tool to identify and report unused software licenses on Windows desktop computers.
Review the underlined text. If it makes the statement correct, select "No change is needed." If the statement is incorrect, select the answer choice that makes the statement correct.

A. No change is needed.
B. System Center Configuration Manager (ConfigMgr)
C. Microsoft Operations Management Suite (OMS)
D. Microsoft Assessment and Planning Toolkit (MAP)
E. System Center Operations Manager (OpsMgr)

Answer: B

QUESTION 32
Hotspot Question
You are developing a SAM program improvement strategy for a customer. Each department manages software license acquisition for their employees.
You must optimize the software license acquisition process. The process must meet the following requirements:
Increase governance of the software license acquisition process. Reduce effort required to manage software license acquisition.
Reduce cost of software license purchases.
You need to provide software and purchasing recommendations to the customer.
What should you recommend? To answer, select the appropriate options in the dialog box in the answer area. Note: Each correct selection worth one point.

Answer:

QUESTION 33
Hotspot Question
An organization plans to implement a SAM program.
You lead a discussion about the program. All executive stakeholders, finance, and IT managers attend the initial discussion.
You need to present a proposal for the SAM project to the organization and complete the necessary prerequisite tasks before the project begins.
For each of the following statement, select Yes if the statement is true. Otherwise, select No. Note: Each correct selection is worth one point.

Answer:


!!!RECOMMEND!!!
1.|2018 Latest 70-713 Exam Dumps (PDF & VCE) 52Q Download:
https://www.braindump2go.com/70-698.html
2.|2018 Latest 70-713 Study Guide Video:

YouTube Video: YouTube.com/watch?v=4krVp0Z0_VY 1

Links:
  1. http://www.youtube.com/watch?v=4krVp0Z0_VY
Post date: 2018-05-09 01:37:42
Post date GMT: 2018-05-09 01:37:42

Post modified date: 2018-05-09 01:37:42
Post modified date GMT: 2018-05-09 01:37:42

Export date: Sat Nov 23 1:49:22 2024 / +0000 GMT
This page was exported from Braindump2go Free Exam Dumps with PDF and VCE Collection [ https://www.mcitpdump.com ]
Export of Post and Page has been powered by [ Universal Post Manager ] plugin from www.ProfProjects.com